Area
360° Service
- Design
- Construction
Place
- Sesto al Reghena (TV)
Construction year
- 2004
Plant performance
-
- Population Equivalent: 16000
- Daily Output: 800 M3/Dd
- COD In: <2000 Mg/L
- COD Out: <100 Mg/L
- Receiver: Surface Water Body
Need
The existing activated-sludge treatment plant was undersized and did not comply with the standards required by law as for discharge to land.
Solution
Because of the need of incrementing the system capability maintaining the existing tanks, in compliance with the strict limits set by law, we deemed necessary to upgrade the plant with the MBR technology.