Area
Place
- Spilimbergo - Italy
Construction year
- 2023
Plant performance
-
- Abitanti Equivalenti: 30
- Portata giornaliera: 2 m3/gg
- COD in: 1.500 mg/l
- COD out: <100 mg/l
- Corpo ricettore: terreno
Need
The client required the design a new waste water treatment plant, really capable of removing physosanitary products that are washed off the spraying field vehicles during cleaning operations, in order to guarantee treated water complying with soil discharge regulations. Client’s main requirements were reliability, compactness and ease of operation.
Solution
CID developed, in collaboration with the Client, a brand new project, designing a compact and simple pre-built buried concrete plant containg pretreatment stages and MBR (ultrafiltration) aerobic stage.
All of the machines and instruments are installed inside a concrete cabinet placed beside the buried plant.